Imagine a brush factory receiving five orders on the same day for producing different brushes such as 2000 flat brushes, 800 toilet brushes, 1000 industrial polishing brushes, 300 customized curved brushes and 1000 small household brushes.
The factory may have a capable brush manufacturing equipment, experienced operators and sufficient raw materials yet production can still become difficult. Because the problem is not simply how fast the machine can produce brushes.
If you are a production manager, you have to decide that which product should be made first and which products can use the same machine setup as well as where fixtures should be changed. This is the reality of multi-variety, small batch brush manufacturing.
Here you need to understand that, in high-mix, low volume production setup and changeover time can become significant part of the available production time. The manufacturing scheduling therefore needs to consider not only the quantities and due dates but also machine capacity and changeover requirements.
The small batch production is very difficult as compared to the large batch production because changing from large batch to smaller one may require change in fixtures, configurations and materials as well as in parameter adjustments.
A factory may have technically available machine hours but still can lose significant productive time through repeated changeovers.
The most effective approach of production is producing products at the right product on the right machine in the right sequence at the right time.
If you are the production manager, before creating the production schedule division of incoming orders into meaningful and useful categories is very essential.
| Classification | Example | Scheduling Consideration |
|---|---|---|
| Product family | Flat cleaning brushes | Group similar products |
| Geometry | Curved/irregular brush | Check machine capability |
| Brush type | Toilet, disc, roller, block brush | Match appropriate equipment |
| Batch size | 200–1,000 pieces | Minimize excessive setup |
| Batch size | 10,000+ pieces | Longer production run may be practical |
| Material | Different filament types | Consider material preparation |
| Fixture | Standard/custom fixture | Group compatible jobs |
| Urgency | Standard/urgent order | Reserve capacity where necessary |
| Quality requirement | Standard/special inspection | Include inspection time |
This simple classification can help you in transforming a long list of customers’ orders into a manageable production plan.
Every order should have a basic production record such as quantity, machine used, customer number, product name, quantity, brush dimensions and required delivery date. The production scheduling can be done in best way by evaluating all orders together as indicated in example table below.
| Order | Product | Quantity | Machine | Setup | Production Time | Due Date |
|---|---|---|---|---|---|---|
| A01 | Flat cleaning brush | 2,000 | Machine 1 | 25 min | 4 hr | Day 2 |
| A02 | Toilet brush | 800 | Machine 2 | 40 min | 3 hr | Day 3 |
| A03 | Industrial brush | 500 | Machine 2 | 50 min | 2.5 hr | Day 2 |
| A04 | Custom curved brush | 300 | Machine 3 | 60 min | 3 hr | Day 4 |
| A05 | Household brush | 1,000 | Machine 1 | 20 min | 2 hr | Day 3 |
It must be noted that, actual time and setup depends entirely on the factory and can vary from machine to machine as well as region wise.
One of the most common mistakes in planning is the assumption that an eight-hour shift provides eight hours of production because time could be reduced by breaks, breakdowns, changeover, maintenance and material handling as well as quality checks. A simple planning equation becomes
Net Available Production Time=Scheduled Shift time−Planned Non−Production Time
For example, 8- hour shift has 480 minutes
If planned breaks, maintenance and other activities consume 60 minutes, net available power becomes.
Net available Power=480−60=420
One of the best and easiest way of production scheduling is the family-based production sequencing instead of producing flat brushes, toilet brushes, flat brushes, industrial brushes and toiler brushes. Produce flat brush products at once and plan to reduce changeover time. The production scheduling sequence must consider;
The higher machine utilization sounds attractive, but 100% utilization is not always the best because machine can be occupied with wrong product, excessive inventory and reworking. A better approach of measuring machine utilization is the measurement of several indicators.
Machine Utilization=Actual Operating timeAvailable Scheduled time×100
The machine utilization alone does not indicate the whole story keeping the track record of good output, rejection rate and downtime and rework is also important.
The modern brush manufacturing equipment can support multiple product types, but flexibility should be understood realistically. For example, some brush machines use interchangeable platforms and stored production programs to support different brush products and short-run production.
The stored programs in machines mean that every physical changeover becomes automatic and operators need to change fixtures, change components, load materials, select programs, adjust settings and verify the first pieces.
You must consider machine flexibility in production planning without assuming zero setup time.
For a brush factory producing different products in relatively small quantities, efficient equipment and utilization means that every brush making machine is busy all the day. The real challenge in this situation is the coordination.
A good production schedule starts with the understanding of the products and their processing requirements. A good production schedule has grouping of jobs, reduced unnecessary changeover, prepared fixtures and materials.
About MX Brush Machinery
MX Brush Machineries specialize in advanced brush manufacturing solutions designed for the modern production environments. From high-performance CNC brush making machines and multi-axes linkage brush machines for fully custom brush making machines. MX Brush Machines help manufacturers in improving production efficiency, enhancing product quality and adapting to market demands. Whether you are looking for single brush making machine or a complete automated production line, MX Brush Machinery provide you reliable equipment, technical expertise and dependable after-sales support to help your business grow.
QUICK LINKS
PRODUCTS
CONTACT US
Contact Person: Leo
Email: Mxdx@Mxbrushmachinery.Com
Tel: +86 13232438671
Skype/Facebook: +86 13232438671
Fax: 0750-6575221
Address: Heqiaolingwu Road, Sanyi Industrial Estate, Siqian Town, Xinhui District, Jiangmen City, Guangdong Province, China (Pc:529159)Pe 2019